November 10, 2009 - 17:34 AMT
Equipment delivery to Hrazdan-5 to finish by year end
In the frameworks of Hrazdan-5 project, energy bloc under reconstruction is being supplied with technological equipment, including GT13E2 Alstom equipment set (total weight: about 1350 tons) for gas turbine and 4 equipment settings for main power transformers, ArmRosgazprom CJSC's press service reports.

Equipment delivery is to finish early in December. Delivery of 400 Mwt power transformer (260 tons) and 5.3 Mwt gas turbine transformer is expected between November 25 and 29, 2009, and the second stage of delivery of gas turbine supplies is to finish by December 10.

Shipping is carried out by SCR CJSC and its specialized subcontractor Rail Gas Service on competitive bases. Supplies are delivered to Batumi port (Georgia) by special sea vessels and then moved to Hrazdan-5 construction site by railway transportation means and automobiles.